Northfield Civil Engineering Ltd

Early Warning Notice

Secure Document
🎯 DEMO MODE - This is a preview with mock data. No changes will be saved.
Back to demos

Early Warning Notice

EW-2024-003

high Risk Awaiting Response

Unforeseen Rock Formation Encountered

Project

Manchester Northern Gateway

Issued By

James Wilson

Issued Date

05/11/2024

Response Required By

12/11/2024

Cost Impact

£15,300

Time Impact

Programme affected

Quality Impact

None identified

Description

During excavation works for the main drainage run (Plot 45-52), we have encountered an extensive rock formation at a depth of 2.5m below existing ground level.

This formation was not identified in the site investigation report provided at tender stage. The rock extends across approximately 45 linear metres of the proposed drainage route.

The formation will require rock breaking and specialist plant to remove, which will have significant impact on both programme and costs.

Cause

Insufficient ground investigation at tender stage

Programme Impact

2-3 weeks delay to drainage installation programme. Critical path impact likely.

Your Response is Required

Please review this early warning and provide your response. This helps manage project risk proactively.