Construction Payment Schedule Calculator (UK)

Build a whole contract payment schedule: every valuation date, due date, payment notice deadline, pay less deadline and final date for payment under JCT, NEC4 or the Scheme. Export to Excel or your calendar.

Leave blank to use the standard-form default of 17 days. Contract particulars amend this routinely.

PeriodEnd of the relevant periodPayment due datePayer's payment notice deadlinePay less notice deadlineFinal date for payment
106/09/202613/09/202618/09/202623/09/202630/09/2026
206/10/202613/10/202618/10/202623/10/202630/10/2026
306/11/202613/11/202618/11/202623/11/202630/11/2026
406/12/202613/12/202618/12/202623/12/202630/12/2026
506/01/202713/01/202718/01/202723/01/202730/01/2027
606/02/202713/02/202718/02/202723/02/202702/03/2027

How these dates are worked out

  • The Scheme applies where the contract has no compliant payment mechanism of its own.
  • The due date is the later of 7 days after the end of the relevant period and the date you make your claim (paragraph 4).
  • The Construction Act counts calendar days. These dates are not shifted for weekends or bank holidays unless your contract says they are.
  • Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule Part II, paragraphs 4, 8, 9 and 10 — legislation.gov.uk/uksi/1998/649/schedule/part/II
  • Housing Grants, Construction and Regeneration Act 1996, Part II, ss.109–111 (as amended by the Local Democracy, Economic Development and Construction Act 2009) — legislation.gov.uk/ukpga/1996/53/part/II
Back to Get Paid on Time

Construction Payment Schedule Calculator FAQ

JCT Standard Building Contract with Quantities 2016, JCT Design and Build 2016, NEC4 Engineering and Construction Contract, and the Scheme for Construction Contracts default that applies where a contract has no compliant payment mechanism of its own.
Enter the number of days your contract gives and the whole schedule recalculates. The standard-form default is shown as the placeholder, so you can see what you are overriding.
No. The Construction Act counts calendar days and none of these standard forms shift a payment deadline for a non-working day. JCT moves an Interim Valuation Date to the nearest Business Day, but the day counts that run from it are calendar days. If your contract says otherwise, adjust the dates.
Yes. The "Add to Calendar" button downloads an .ics file with an all-day entry for every due date, payment notice deadline, pay less deadline and final date for payment in the schedule. It imports into Outlook, Google Calendar and Apple Calendar.