Home/Resources/Get Paid on Time/retention in construction

Retention in Construction: How It Works and How to Manage It

What retention is in UK construction, typical percentages, half and full release timings, and practical advice for managing retention across multiple projects.

Overview

Retention is money withheld from interim payments as security against defects. It is standard practice in UK construction, but it ties up significant cash and causes real problems when it is not tracked or released on time. This guide explains how retention works, what the typical terms are, and how to manage it properly across your projects.

What Is Retention in Construction?

Retention is a percentage of each interim payment that the payer holds back as a financial incentive for the contractor or subcontractor to complete the work and rectify any defects. It is not a penalty -- it is a form of security. The money is held in trust (or should be) and released in stages once the work is satisfactorily completed.

  • Typically 5% of each interim valuation (some contracts use 3%)
  • Withheld from each payment application during the project
  • Half is released at practical completion
  • The remaining half is released at the end of the defects liability period (usually 12 months)
  • The employer holds retention on behalf of the contractor -- it should not be treated as a discount

Half Retention Release (Practical Completion)

When practical completion is certified, half of the total retention is released in the next payment. This recognises that the building or works are substantially complete and fit for use. The contractor should check that the retention release is included in the next payment certificate.

  • Triggered by the certificate of practical completion
  • Half of the total retention held is released
  • Should appear in the next interim payment or certificate
  • Chase promptly if it does not appear -- delays are common
  • Check the contract for the exact mechanism and timing

Full Retention Release (End of Defects Period)

The remaining retention is released after the defects liability period ends, provided any notified defects have been rectified. On most contracts this is 12 months after practical completion. Subcontractors often have to wait for the main contractor to release retention, which can add further delay.

  • Typically 12 months after practical completion (check your contract)
  • Requires a certificate of making good defects or equivalent
  • Defects must have been rectified to the satisfaction of the contract administrator
  • Subcontractor retention release depends on the main contract terms
  • If defects are not notified within the period, retention should be released in full

Common Retention Problems

Retention is one of the most common sources of cashflow frustration in UK construction. Contractors and subcontractors frequently report late release, unjustified withholding, and difficulty tracking retention across multiple projects and clients.

  • Late release: retention not paid on time despite defects being rectified
  • Unjustified withholding: retention held beyond the defects period without valid reason
  • Insolvency risk: if the employer or main contractor becomes insolvent, retention may be lost
  • Poor tracking: retention across 20+ live projects is difficult to manage on spreadsheets
  • Subcontractor squeeze: main contractors delay releasing retention even after receiving it
  • No trust account: retention is often not held in a separate account despite recommendations

How to Manage Retention Effectively

Good retention management starts with tracking it from the first interim payment. Know how much is held on each project, when half release is due, when full release is due, and chase it on time. Retention you forget about is retention you may never get back.

  • Record retention held on every interim payment application
  • Track practical completion dates and half release due dates per project
  • Track defects liability end dates and full release due dates per project
  • Set calendar reminders or use software alerts for release milestones
  • Chase retention proactively -- do not wait for the payer to offer it
  • Keep records of all defect rectification work as evidence for release

Key Takeaways

  • Retention is typically 5% of each valuation, released in two halves
  • Half is released at practical completion, the rest after the defects liability period
  • Late and unjustified retention withholding is a major cashflow issue in UK construction
  • Track retention from the first payment on every project -- do not leave it to the end
  • Chase releases on time with evidence of completion and defect rectification

Track retention across every project automatically

Site Samurai turns these templates into automated workflows with deadline tracking and audit trails.

Frequently Asked Questions

Is retention money held in trust?
It should be, but in practice many employers and main contractors do not hold retention in a separate trust account. The Construction Act does not currently require it, though industry bodies have campaigned for change. If the payer becomes insolvent, unsecured retention may be lost.
Can I refuse to accept retention in my contract?
You can negotiate on retention terms before signing. Some contractors accept lower retention percentages, retention bonds instead of cash retention, or project bank accounts. Your bargaining position depends on market conditions and the client relationship.
What is a retention bond?
A retention bond is a guarantee provided by a bank or insurer instead of cash retention. The contractor pays a premium for the bond, and the employer can call on it if defects are not rectified. It keeps cash in the contractor's business instead of being held by the employer.
Can Site Samurai track retention across projects?
Yes. Site Samurai tracks retention held, practical completion dates, and defects liability periods across all your projects. You get visibility of total retention outstanding and alerts when release milestones are approaching.

Ready to Automate Your Workflows?

Site Samurai turns these templates into automated workflows with deadline tracking, audit trails, and team collaboration.